It’s construction season and County of Renfrew officials are advising the public about projects that are set to start or just around the corner.
Upcoming projects include:
County Structure C001 (Berlanquet Creek Culvert) – Township of Admaston/Bromley
The rehabilitation of County Structure C001 (Berlanquet Creek Culvert), located on County Road 5 (Stone Road), approximately 4km west of Highway 132, is anticipated to commence the week of July 15 and be completed in late September. During construction, the road at the structure will be temporarily closed to traffic with an alternate route, using Foy Road and Culhane Road, posted.
County Structure C339 (Lynch Road Culvert) – Township of Admaston/Bromley
The replacement of County Structure C339 (Lynch Road Culvert), located on Lynch Road, approximately 3km south of County Road 5 (Stone Road), is anticipated to commence the week of July 8 and be completed in late July. During construction, the road at the structure will be closed to traffic with an alternate route, using County Road 5 (Stone Road) and McNulty Road, posted.
County Structure C134 (Campbell Drive Culvert) – Township of McNab/Braeside
The rehabilitation of County Structure C134 (Campbell Drive Culvert), located on Campbell Drive, approximately 3km west of Highway 417, is anticipated to commence the week of July 15 and be completed in late September. During construction, the road at the structure will be limited to a single lane of alternating traffic.
County Road 19 (Mud Lake Road) – Township of Laurentian Valley
The rehabilitation of County Road 19 (Mud Lake Road), from County Road 24 (White Water Road) to the City of Pembroke boundary, is anticipated to commence this week and be completed in late July. During construction, the road will be reduced to a single lane of traffic in locations.
County Road 30 (Lake Dore Road) – Township of North Algona/Wilberforce
The rehabilitation of County Road 30 (Lake Dore Road), from Sperberg Road to Trailblazers Road, is anticipated to commence the week of July 29 and be completed in early September. During construction, the road will be reduced to a single lane of traffic in locations.
County Road 515 (Palmer Road) – Township of Madawaska Valley
The rehabilitation of County Road 515 (Palmer Road), from County Road 62 (Combermere Road) to Finch Road, is anticipated to commence the week of Aug. 5 and be completed in early September. During construction, the road will be reduced to a single lane of traffic in locations.
County Structure B108 (Tramore Bridge) – Township of Killaloe, Hagarty and Richards
The rehabilitation of County Structure B108 (Tramore Bridge), located on Tramore Road, approximately 0.25km north of County Road 58 (Round Lake Road), is anticipated to commence the week of July 15 and be completed in early October. During construction, the road at the bridge will be closed to traffic with an alternate route, using County Road 58 (Round Lake Road) and Highway 60, posted.
For up-to-date information on active projects and their traffic impacts, please visit Municipal511.
Please contact the Department of Public Works and Engineering department should you have any questions or concerns about a county construction project or general operations.
(Sherry Haaima)